![]()
| Project Name: | Runway 11-29 Overlay and Taxiway W Conversion |
| Location: | Port of Oakland, CA |
| Project Description: | The
Project consists generally of construction of overlay of Runway 11-29 and
conversion of Taxiway W to temporary Runway 12-30, at the south Field. The
work consists of a six-inch overlay of Runway 11-29 and the conversion of
Taxiway W to temporary Runway 12-30 for use during the period of the overlay
of Runway 11-29. The work was performed in multiple phases to minimize disruptions
to aircraft operations.Schedule of Work (Phasing): Phase I: Converted Taxiway W between Taxiway U & V to a 150 foot wide taxiway suitable for use as a runway including installation of temporary and permanent light fixtures. This phase of the work is scheduled for 24 calendar days. Phase II: Converted the north half Taxiway W not between Taxiway U & V to a 150-foot wide taxiway suitable for use as a runway including installation of temporary and permanent light fixtures. This phase of work is scheduled for 13 calendar days. Phase III: Converting the remaining south half Taxiway W not between Taxiway U & V to a 150 foot wide taxiway suitable for use as a runway including installation of temporary and permanent light fixtures. This phase also requires the final striping of the taxiway as a runway. This phase of the work is scheduled for 8 calendar days. Phase IV: Overlaying the existing Runway 11-29 with approximately 6 inches of asphalt. This phase of the work is scheduled to start no earlier than August 4, 2001 and to be completed no later than August 30, 2001. Phase V: Converted Taxiway W back to a taxiway including removal of runway markings and permanent light fixtures. This phase of the work is scheduled for 14 calendar days. Phase VI: Completed the grooving of the newly over-laid runway. This phase of the work is scheduled for completion over a period of 19 consecutive Monday night closures. |
| Paragon's Role: | As
Prime Consultant, Paragon coordinated an extensive Team effort to
overlay a 10,000-foot runway for the Port of Oakland in just five days.
This $10 million dollar project was completed ahead of the Port's original
10-day schedule. An existing taxiway was converted to serve as temporary
runway to avoid complete shutdown of operations while the overlay was being
placed. Approximately 104,000 tons of asphalt was overlaid as well as raising
or replacing over 650 center and edge lights. Our construction management
staff along with the contractor, and other key sub-consultants participated
in an extensive planning effort well in advance identifying all potential
conflicts and establishing back-up procedures. This project resulted in
significant time and cost savings to the client. |
| Owner/Client: | Port
of Oakland1749 Harbor Road, Bldg D833 Oakland, CA 94607 |
| Project Duration: | May
2001 - January 2002 |
| Constructed Value: | $14,438,383 |
| Video: | Comments
by Steve Grossman - Director of Aviation, Oakland International Airport Clip 1 Clip 2 Clip 3 Clip 4 To
view these clips, you must have Real
Player installed.Click here for your free copy. |
|
« Back |