| Project Name: | Taxiway A Reconstruction |
| Location: | John Wayne Airport, Costa Mesa, CA |
| Project Description: | The
project included reconstruction of Taxiway "A" between Taxiway "G" and Taxiway
"J" including replacement of existing asphalt pavement with concrete pavement.
Work was performed in a busy airport operations environment with significant
safety and operations concerns. The project was completed with no lost time
accidents and no unanticipated interruptions to airport operations. The
project closeout time was less than one month for quantity and test reconciliation. |
| Paragon's Role: | As
Construction Management Consultant, Paragon provided airfield engineering
and construction support services for Taxiway "A" Reconstruction adjacent
to the South RON. Specific services included quality assurance inspection,
coordination with airport operations, testing laboratory, and surveyor;
measurement for payment, quantity tracking, daily progress reports, weekly
progress reports, monthly FAA reports, project progress photos, and progress
closeout report for test and quantity reconciliation. |
| Owner: | John
Wayne Airport3160 Airway Avenue Costa Mesa, CA 92626 |
| Client: | URS Greiner
Woodward Clyde 2020 East First Street #400 Santa Ana, CA 92705 |
| Project Duration: | June 2000 |
| Constructed Value: | $5 million |
|